Home | Site Map | Glossary  
 

Infrastructure: Large Projects

EPWSP Programmes (Years 1-4)
 
 
     

Purpose of the sub-programme

The purpose of this sub-programme was to develop and implement a methodology for undertaking large infrastructure projects labour intensively, using small and medium enterprises.

Work undertaken

This sub-programme was originally called the Private Sector Mobilization Programme whose purpose was to encourage the private sector to participate effectively in the EPWP infrastructure sector. The programme intended to obtain the commitment of private sector investors to ten large labour intensive projects and promoting training and awareness of the EPWP by established and emerging contractors.

During Year 1, discussions were undertaken with the largest players in the construction industry to determine the feasibility of implementing the programme. Generally stakeholders were not positive about the Support Programme being able to convince the private sector to undertake large labour intensive projects. At the same time, Cabinet raised concerns about the small size, limited impact and visibility of EPWP projects, and identified a need to expand the EPWP beyond its current implementation framework. In response to these concerns, the EPWP Unit was mandated to produce proposals for a mechanism to enable larger EPWP projects. Consequently, the Support Programme was approached to assist the Unit in developing a position paper on this issue through the STAF. The assignment comprised an engagement process with key stakeholders in the construction sector and the development of proposals. The proposals recommended utilizing the capacity and skills of large established contractors, in a manner that empowered, trained and provided mentorship to emerging contactors. It was determined that the approach had the potential to create an additional 150 000 person-years of employment.

On the basis of the work undertaken it was evident that the impact of using large contractors to implement public sector infrastructure projects, was likely to be greater than the time and effort that would be needed to identify and convince private sector investors to undertake labour intensive projects. Accordingly it was determined that the Private Sector Mobilization Programme should be refocused to recognize the more significant contribution large construction contractors, rather than investors can make to the EPWP.

The initial concept was approved by Cabinet Legotla in January 2006. As part of the revised Private Sector Mobilization Programme, now called the Large Projects Programme, a Service Provider was contracted by the Support Programme to develop the procurement procedures to enable the approach to be tested through a pilot project. The procurement procedures were developed but finding an appropriate pilot project took an extensive amount of time and there were many stops and starts. Finally a three year R500 million water pipe replacement project in eThekwini was identified and technical support was provided by the Support Programme to assist in structuring the project. During Year 3 Ninham Shand was appointed as the Programme Manager and four large contractors were appointed to manage the project each in a specific region. Each of the large Contractors is required to contract and mentor 4 to 5 sub-contractors. A Reference Group was established to oversee the implementation process and draw learning’s for the future of the programme.

The Support Programme continued to monitor the implementation of the pilot project until the end of year 4 and documented learning’s for dissemination to other Municipalities with an interest in implementing such projects.

The Support Programme developed a list of “lessons” from this pilot project, so that the concept could be applied more widely by the EPWP Unit. The EPWP Unit has now set up a dedicated directorate to support the adoption of this approach by Provinces. This Large Projects Unit has taken on the supervision of the Large Contractor Model being used in eThekwini and has began to promote it nationally. The Support Programme has worked with the Unit to assist them to develop a strategy for monitoring this work.

Achievements

As a result of this sub-programme a methodology for involving large contractors in the EPWP on a basis where smaller contractors continue to be utilized and labour intensive projects are undertaken was developed and piloted.

This methodology is now being rolled out by a dedicated directorate in the EPWP Unit.

Lessons learnt

While the Large Contractors Programme offers significant opportunities to public bodies to improve their delivery efficiencies, it is critical that careful monitoring of these projects to maximise the labour intensity and job creation opportunities is applied, as this is not necessarily the driving interest of public bodies wishing to apply the model.

Significant support to public bodies is required in the preparing of the contract documents, as inclusion of all the developmental objectives the Large Contractor is expected to achieve must be clearly specified. In addition, monitoring the reporting of the contractor against these deliverables is essential.

The application of the EPWP MIS as a required reporting tool significantly assisted eThekwini officials in ensuring that the contractors did report all work opportunities.

   
     

 


     
To contact the Expanded Public Works Support Programme:
Ms Afsaneh Tabrizi Afsaneh@shisaka.co.za
Telephone +27 (0)11 447-6388
Facsimile +27 (0)11 447-8504
Physical Address   Shisaka Development Management Services
3rd Floor
132 Jan Smuts Avenue
Rosebank
Johannesburg
South Africa