Home | Site Map | Glossary  
 

Infrastructure: Linkages Project

EPWSP Programmes (Years 1-4)
 
 
     

Purpose of the sub-programme

The Linkages Project aimed to develop a practical system for EPWP workers to access training opportunities.

Work undertaken

A key component of the first phase of the EPWP was to provide a training benefit to each worker in addition to their work opportunity. However since inception the EPWP consistently failed to meet its training targets. Accordingly this sub-programme aimed to develop a practical system for EPWP workers to access their training benefit in the Infrastructure sector.

In 2007 a pilot project commenced with the eThekwini Metro, the KZN Department of Transport, the National EPWP Unit and the KZN Department of Labour to test how EPWP municipal projects could more effectively access and use the Department of Labour (DoL) and SETA allocations for training. The intention was to develop a set of procedures by which training needs are identified and funding secured. This process led to a greater understanding of the difficulties faced in accessing training using current procedures.

By the end of 2007 the pilot concluded that the model of requiring public bodies to engage with the DoL funding application was unrealistic and virtually impossible. A set of recommendations were developed and presented to DPW, DoL and EPWP Provincial Officials. A number of these recommendations were implemented. In addition partly as a result of these findings training as an objective of the EPWP was not carried through to the second phase of the EPWP.

Achievements

This project led to a greater understanding of the difficulties faced in accessing training using current procedures and resulted in a revised approach to training. In particular the issue of training was recognized to be a project specific requirement to ensure that workers could perform their tasks effectively in a manner that did not undermine their health or safety. This revised approach to training was incorporated into the design of the second phase of the EPWP.

Lessons learnt

The benefit of this programme was that it allowed a number of different stakeholders to work collectively to try and resolve a problem. A team of highly skilled consultants worked with and reported to a team that comprised representatives from the:

  • eThekwini Metropolitan Municipality
  • National EPWP
  • Provincial EPWP
  • Department of Labour
     

The pilot was able to demonstrate that the reason municipal infrastructure projects were unable to achieve the training targets was not because of a lack of will or capacity, but because the institutional arrangements on which the programme was premised were inadequate. Being able to demonstrate this to all relevant parties, all of whom had engaged in trying to resolve the problems, took much of the heat and tendencies to “blame” different parties out of the training debate at the national EPWP Unit. It also suggested very clearly that public bodies should only be responsible for delivering activities that were clearly within their own mandate.

   
     

 


     
To contact the Expanded Public Works Support Programme:
Ms Afsaneh Tabrizi Afsaneh@shisaka.co.za
Telephone +27 (0)11 447-6388
Facsimile +27 (0)11 447-8504
Physical Address   Shisaka Development Management Services
3rd Floor
132 Jan Smuts Avenue
Rosebank
Johannesburg
South Africa