Home | Site Map | Glossary  
 

Infrastructure: Public Sector Sub-Programme

EPWSP Programmes (Years 1-4)
 
 
     

Purpose of the sub-programme

The aim of the Public Sector Sub-programme was to ensure that prioritised Municipalities and Provinces set and achieve EPWP targets for training and job-creation in respect of the EPWP.

Work undertaken

The initial intention of this sub-programme was to work with 12 Municipalities, 4 Provincial Departments dealing with Infrastructure (Roads, Works or Transport) and at least 2 State Owned Enterprises.

In 2005 engagement commenced with six Municipalities and two Provinces. The Support Programme appointed Facilitators and Technical Experts to work in each Municipality and Province with a focus on assisting them to identify and implement labour intensive EPWP infrastructure projects and to report on the work opportunities generated to the EPWP Unit. The process included identifying those projects that were blocked from being implemented and finding ways to resolve these blockages. To assist this process, the Support Programme developed a Management Information System (MIS) to monitor project implementation progress. In addition engagements commenced with State Owned Enterprises.

By the middle of 2006 it was clear that Municipalities and Provinces face different challenges and have a different focus in respect of implementing EPWP projects. Accordingly it was agreed that the Public Sector Sub-programme should focus only on Municipalities and a new sub-programme (Provincial Roads) should be implemented with a focus on Provinces (see below). In addition after a number of interactions with State Owned Enterprises it was decided that these entities were insufficiently interested in engaging around the EPWP and that support resources would be better focused elsewhere.

With respect to the Provinces, a key learning of the Support Programme as a result of its interactions during this period was that the programme had been engaging with the wrong Officials in the Province and that was why success had been limited. The Support Programme engaged with the officials in the EPWP Unit of the Province. However these Officials did not have line accountability for implementing EPWP projects and were not in control of the budgets. Accordingly their ability to influence decisions was limited. The Support Programme came to understand that in order to be more effective there was a need to support those Officials that had the budget and accountability for directly implementing EPWP projects. This finding was applied in respect of the Provincial Roads Programme (see below)

By the end of 2006 the activities undertaken by the Support Programme had led to a clear understanding of the core functions that are required in order to support Municipalities to implement the EPWP. These functions included:

  • Ensuring that there is a will and commitment from senior personnel in the Municipality to meet EPWP targets.
  • Facilitating relationships across the municipality to support the planning, implementation and reporting of EPWP work opportunities through a management information system.
  • Providing engineering support to the Municipality to expedite project delivery and labour intensive design and implementation.
  • Developing and operating a management information system to record EPWP projects, their progress in implementation and the number of work opportunities that they provided per quarter.
     

In addition a methodology had been developed by the Support Programme as to how this support could be provided to a Municipality. The Support Programme also determined that the intensity of the resource required to enable municipal delivery was substantial. It was therefore decided that there was no further value in the Support Programme itself extending its activities to additional Municipalities. Rather a process was put in place whereby the EPWP Unit would procure technical resource which could work with additional municipalities.

While the Support Programme continued to work directly with selected Municipalities, at the same time it began to work with the EPWP Unit to put in place a “Joint Engagement Strategy” whereby the Support Programme and EPWP Unit would work together to offer the support to 45 municipalities with the highest MIG allocations. This required ‘translating’ the methodology being applied by the Support Programme into a methodology that would be appropriate for a public entity and could be applied at scale.

At the start of 2007 implementation of the Municipal Joint Engagement Strategy commenced on the following basis:

  • The Support Programme continued to provide direct support to four Municipalities
  • The EPWP Unit procured the services of Virtual Inkhanyiso to provide technical support through a structure to be called the ‘National Technical Support Team’. Work began initially with 41 municipalities and over time expanded to 130.
  • The Management Information System developed by the Support Programme was adapted to support all participating municipalities, with the Support Programme retaining management responsibility for the system. This system comprises a national internet based monitoring and information system, together with a DataBureau that verified information being put onto the system and produced progress reports on the data loaded.
     

By 2008 the systems, processes and procedures developed by the Support Programme through the Public Sector Sub-Programme had been fully adapted and taken over by the EPWP Unit who continued to run the sub-programme as one of their permanent activities. The Support Programme exited the last of the direct engagements with municipalities, but continued to run the DataBureau and MIS and to provide support to the National Technical Team and the EPWP Unit in undertaking the programme.

During 2009 the MIS system and DataBureau adjusted for the second phase of the EPWP. The Support Programme handed over the system to the EPWP Unit in 2010.

All of the above work was undertaken in close cooperation with the EPWP Unit. Task Team meetings were held monthly to agree the work to be undertaken and monitor progress.

Achievements

Key achievements in respect of this sub-programme include the following:

  • The Support Programme worked with six municipalities and two provinces, assisting them to identify and facilitate labour intensive EPWP infrastructure projects.
  • The Support Programme developed a Monitoring and information System and Data Bureau to report EPWP projects, monitor progress and identify blockages. This system is being used by the EPWP Unit in the implementation of the second phase of the EPWP.
  • Based on the lessons learnt, the EPWP Unit rolled out the approach developed by the Support Programme with its own Technical Support Team to 110 Municipalities. The Support Programme provided ongoing support to this process in hosting the MIS, quality assuring all data and setting up all required monitoring processes to monitor the support.
  • A target management process aimed at ensuring that senior leadership manage target achievement was developed and adopted by the EPWP Unit.

Lessons learnt

Through this sub - programme the Support Programme identified, developed and applied critical lessons about the functions required for effective support to Municipalities to create and report work opportunities and the capacities required to effectively undertake these functions.

These learning’s were initially learnt through the direct engagement with the original six municipalities, and then refined through ongoing application and review with the EPWP Unit and the National Technical Support Team. Finally, the learning’s were applied in the development and implementation of the incentive grant during the second phase of the EPWP.

The learnings are as follows:

1) Prioritise the areas where EPWP delivery can most likely be achieved:

  • Initially, provide support to the institutions with the best chance of succeeding.
  • Prioritise projects which are already labour intensive, or where there are standard or explicit ways for increasing labour intensity (i.e. as set out in the EPWP Guidelines).
  • Allocate expensive resources (such as engineering support) only in the places where there is a will and capacity to implement EPWP principles.
     

2) Establish clear targets for EPWP delivery:

  • Targets should be explicit,
  • Targets should be agreed by senior management (MMC or Portfolio Councillor),
  • Achievement of the targets should be actively monitored, and
  • Achievement of the targets should lead to recognition and affirmation.
     

3) Formalise agreements on support :

  • The support to be provided should be explicitly defined and agreed.
  • Provision of the support should be monitored.
  • Support should be withdrawn if there is not mutual participation or appreciation of the activities from the entity being supported.
     

4) Maintain all information on one single project database:

  • The Management Information System allowed one database of projects to be reviewed by the EPWP Unit at all times- to monitor both the anticipated EPWP delivery; and the actual performance at any one time of any public body towards its targets.
  • This database of projects was fully visible to any stakeholder interested in viewing it and immediately allayed fears that the EPWP Unit was reporting invalid data.
  • As the programme developed, options were developed to enable national EPWP staff, deployed resources (e.g. technical consultants and or data capturers), municipal staff or others delegated by them to enter data. This was useful in increasing the ease by which data could be loaded. However it required the need to maintain ruthless integrity in:
    • Ensuring data validity.
    • Monitoring the system to show where there was movement or not.
    • Incorporating “authoriser” functions, to ensure public bodies explicitly authorised information loaded on their behalf.
    • Identifying projects and public bodies which were not updating information and ensuring interventions were established to resolve this problem.
       

5) Provide dedicated technical/engineering support to municipalities only where collaborative reporting capacity is in place:

Originally, it was understood that the purpose of providing technical support- through the form of qualified civil engineers, would be to assist the municipalities to:

  • Identify projects most suitable for labour intensive implementation.
  • Ensure that the MIG Business Plans or other project documentation allowed for labour intensive engineering methods.
  • Support municipal staff to require labour intensive methods in the contracting documents with consultants and contractors.
  • Monitor application of labour intensive methods and ensure all subsequent work opportunities were reported to the EPWP Unit nationally.
     

The significant lack of engineering capacity in municipalities however often meant that technical support personnel were caught between conflicting priorities:

  • Municipal staff were grateful for their assistance in performing their normal functions- regardless of EPWP or labour intensity.
  • EPWP Staff, caught in the quarterly panic of needing to get jobs reported, wanted them to capture data as their primary objective- from any infrastructure project regardless of their labour intensity.
     

By the end of the fifth year of the programme, it became clear that there is little point in having a technical support capacity, if there is not an equally clear and collaborative reporting capacity in place.

6) Provide Management Reports and Monitor Performance:

A significant learning is the need to ensure that EPWP performance is monitored regularly and not only at the time of submitting reports. The critical milestones for municipalities to monitor, particularly in the second phase of the EPWP, if they are to ensure they receive the maximum amount of incentive grant payments are:

  • Ensuring that projects with sufficient budget are identified for EPWP delivery. The Incentive targets are based on budget allocations, so projects must be identified and loaded onto the MIS with budgets equivalent or more to those used to calculate the incentive targets.
  • Ensuring that projects are progressing through the project preparation milestones and that EPWP work opportunities are planned for. Any delay in the normal project cycle will impact on EPWP achievements. Projects identified as providing opportunities for labour intensity, must be designed by the consulting engineer in a way which maximises the job opportunities. Managers should regularly review their planned projects and ensure that any problems are swiftly dealt with.
  • Ensuring that projects create the work opportunities expected. In addition, that data is captured at site in the correct manner. The incentive grant has stringent requirements for public bodies in regard to its financial and beneficiary reporting. It is therefore essential that managers monitor compliance with these requirements throughout the process.
     

Perhaps the most significant learning however is that many public bodies do not routinely manage the performance of projects, staff or contractors and considerable assistance is required to enable them to do this.

   
     

 


     
To contact the Expanded Public Works Support Programme:
Ms Afsaneh Tabrizi Afsaneh@shisaka.co.za
Telephone +27 (0)11 447-6388
Facsimile +27 (0)11 447-8504
Physical Address   Shisaka Development Management Services
3rd Floor
132 Jan Smuts Avenue
Rosebank
Johannesburg
South Africa